  • Which schedule development tool and technique produces a theoretical early start d...

  • What is the minimum a project schedule must include?

  • What cost control technique is used to compare actual project performance to plann...

  • Using the following data, what is the Schedule Performance Index (SPI)?EV = $500PV...

  • Which enterprise environmental factors are considered during cost estimating?

  • Which process involves aggregating the estimated costs of the individual schedule ...

  • What is the schedule performance index (SPI) using the following data?BAC = $100,0...

  • The project manager calculated a schedule performance index of 0.8 and a cost perf...

  • EAC (estimate at complete) is typically based on actual cost (AC) for work complet...

  • Which of the following equations is used to calculate schedule variance?

  • Which tool and technique uses a statistical relationship between historical data a...

  • Which of the following equations is used to calculate cost variance?

  • Given the following values, what is the calculated expected activity cost (CE) whe...

  • What is the expected activity cost for a project having a most likely cost of $140...

  • What does a SPI value greater than 1.0 indicate?

  • Total funding requirements and periodic funding requirements are derived from:

  • What is the status of the project whose data is shown in the following S-curve?

  • If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV...

  • Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tool...

  • Which tool and technique identifies inefficient and ineffective policies, processe...

Be the first to review
Login and Review
  • info
    Quiz Info
  • date_range
    Feb. 8, 2016, 3:28 a.m.
    help_outline
    20 questions
    dvr
    0 completed
    remove_red_eye
    20 views
    people
    0 takers
    folder

  • ISEB-PM1 Foundation Certificate in Project Management (Exam 21) QR code

Ratings

star_borderstar_borderstar_borderstar_borderstar_border
ratings